Objective
Restore the passenger capacity of Princess Juliana International Airport to pre-Hurricane Irma levels with improved resilience toward hurricanes
Beneficiaries
- Airlines and airport terminal through increased revenue
- Travelers from increased airport capacity and flight availability
- Tourism sector from the recovery of air transport services
- Workers from job creation during and after the reconstruction
Approach




Components
- Reconstruction of the Princess Juliana International Airport Terminal facilities
- Capacity building of and project management by the Princess Juliana International Airport Operating Company
- Capacity building of and project management by the government of Sint Maarten